Points Forts du Projet
- Année de Réalisation
- 2022
- Emplacement
- New Administrative Capital
- Segment Industriel
- Industriel
- Système Installé
- WATER SPRAY
Conformité et Approbations
Étude de Cas d'Ingénierie Complète
Secteur Énergie — Protection des Sites Critiques
Automatic water spray system for 500kV transformers ensuring rapid cooling and suppression.
Le Défi Technique
Protecting strategic 500kV oil-filled transformers in a high-density urban infrastructure project. The risk of oil explosions and cascaded failure required an immediate response system.
La Solution d'Ingénierie
Designed a Deluge Water Spray System utilizing galvanized steel piping rings surrounding each transformer. High-velocity nozzles are strategically aimed to cool the transformer tank and extinguish oil fires simultaneously. Activated by linear heat detection cables.
Résultat et Impact Opérationnel
System successfully effectively isolates fire risks, preventing catastrophic damage to the grid backbone. Commissioned ahead of schedule to support the New Capital's inauguration.